Additional project information

Completed works

  • - HDPE pipelines: 9,772.36 m
  • - Valve reinforced concrete (RC) chambers: 23 units
  • - Connection RC chambers: 38 units
  • - Foundations for pivot irrigation centers: 6 units

Contract value: €2,720,614.33 (excluding VAT)

Contractual deadline

24. 7. 2023. – 23. 11. 2024.