Additional project information

Completed works

  • - Gravity sewer: 1,944.65 m
  • - Sewer inspection manholes: 39 units
  • - Sewer house connections: 84 units
  • - Pressure pipeline: 3,742.58 m
  • - Pumping station Q = 10 l/s – 1 unit

Contract value: €1,021,500.10 (excluding VAT)

Contractual deadline

01.08.2024. – 31.05.2026.